no.
|
project name
|
period (month)
|
project type
|
scale (10000 ton per day)
|
capital source
|
1
|
tianjin xinkaihe waterworks second phase of extension project
|
21
|
supply, installation, debug and test-run of equipment for waterworks
|
50
|
loaned by japan bank for international cooperation
|
2
|
nanjing water supply project
|
16
|
supply, installation, debug of equipment for waterworks
|
20
|
loaned by japan bank for international cooperation
|
3
|
changzhou waterworks extension project
|
18
|
supply, installation and debug of control system
|
10
|
loaned by the world bank
|
4
|
tianjin xinkaihe waterworks second phase of extension project
|
22
|
supply of engineering machine & vehicle
|
50
|
loaned by japan bank for international cooperation
|
5
|
anshan yintang project
|
20
|
supply of technology equipment & automatic control instrument
|
|
loaned by japan bank for international cooperation
|
6
|
guangxi province he country sewage treatment projec
|
25
|
supply, installation, debug and test-run of equipment for waterworks
|
6
|
loaned by asian development bank
|
7
|
beijing ninth waterworks extension project
|
11
|
supply, installation, debug of instrument & automatic control system
|
50
|
loaned by japan bank for international cooperation
|
8
|
liaoning urban infrastructure project
|
5
|
supply & installation of equipment for waterworks
|
|
loaned by the world bank
|
9
|
vietnam hochiming water supply project
|
6
|
supply of pipes and valves
|
|
loaned by asian development bank
|
10
|
dali no.2 waterworks extension project
|
22
|
supply & installation of technology equipment
|
12
|
government loans
|
11
|
changchun no.3 waterworks extension project
|
40
|
civil works & supply,installation debug and test-run of whole sets of equipment
|
22
|
loaned by the world bank
|
12
|
kunming no.6 water treatment plant project
|
12
|
supply, installation, debug and test-run of equipment for waterworks
|
10
|
loaned by the world bank
|
13
|
changchun west sewage treatment plant project
|
9
|
supply, installation, debug and test-run of equipment for waterworks
|
15
|
loaned by japan bank for international cooperation
|
14
|
tangshan center area waterworks project
|
21
|
supply, installation, debug and test-run of equipment for waterworks
|
15
|
loaned by the world bank
|
15
|
tianjin jizhuangzi sewage treatment plant extension project
|
13
|
supply, installation, debug and test-run of equipment for waterworks
|
54
|
loaned by japan bank for international cooperation
|
16
|
control system and instrument of tianjin xianyan road project
|
8
|
supply, installation, debug and test-run of of whole sets of equipment
|
45
|
loaned by japan bank for international cooperation
|
17
|
tianjin xianyang road sewage treatment plant project
|
13
|
supply, installation, debug and test-run of equipment for waterworks
|
45
|
loaned by japan bank for international cooperation
|
18
|
jilin songhua river pollution control project
|
13
|
supply, installation, debug of chemical & detection apparatus and online monitoring system
|
|
loaned by japan bank for international cooperation
|
19
|
tianjin sewage treatment project j package
|
4
|
supply, installation, debug of odor treatment equipment
|
54
|
loaned by japan bank for international cooperation
|
20
|
chongqing tangjiatuo sewage treatment plant second phase
|
18
|
supply, installation, debug and test-run of equipment for waterworks
|
30
|
loaned by japan bank for international cooperation
|
21
|
ningbo beiqu sewage water treatment plant
|
18
|
supply, installation and test-run of equipment for waterworks
|
10
|
raising fund by the end-user
|